Thorburn Australia have been active in Weipa since 2014 after assisting with their C2 Conveyor Upgrade. This project was initially an evaluation of the comparative merits of a VSD over a wound rotor motor. The conclusion in this case, was the use of wound rotor motors with new brush lifting equipment.

Thorburn Australia then went on to the electrical and control design for the new system.

Since that time, we have been utilised for various works including:

• SUB50 3.3kV MCC Upgrade
• Various Light & Power Board designs
• Wind Telemetry replacement
• Submersible Pump Upgrades
• Andoom Process Water Pumps
• Andoom Cyclone Feed Pump

The latest projects executed in 2018, are the Andoom Pumps which require the upgrade of 3x300kW Variable Speed Drives and a 1.5MW, 3.3kV VSD.

Project Features

Programmable Logic Controllers

Allen Bradley Control Logix PLC’s, Bailey’s INFI90 Distributed Control Systems.

SCADA & HMI

Allen Bradley Factory Talk, Schneider Citect, Conductor and Composer Automation Architect.

Communications

AB Stratix switches utilising Resilient Ethernet Protocol (REP). DeviceNet and Ethernet IP to field devices.

Variable Speed Drives

Schneider Altivar and Siemens high voltage Variable Speed Drives.

Telemetry

Miri Technologies AD2000 advanced telemetry modules using UHF digital radios.

MV Switchgear

Upgrades to existing GEC Switchgear to new ABB Unigear ZVC  3.3kV Switchgear. Multilin 369 Protection Relays.